Our projects

Bowral Truck Water Main Duplication

Client: Wingecarribee Shire Council Location: Bowral, NSW Duration: 34 Weeks

Key Components

  • Construction of 380m of 180mm PE & 2km of 400mm PE
  • Installation of inlet control valve and SCDA system
  • Construction of 450mm case bore under an RMS Road
  • 8 connections to the existing water network including old AC mains
  • 48 property services transfers
  • Full restorations of all road surfaces and footpaths
  • Construction of 1.8km of 400mm water main by NDD boring
  • 32m case bore under RMS Road
  • Working in live traffic environments and the public domain

Project Summary

Fluid Services was contracted by Wingecarribee Shire Council to construct a new truck watermain due to the rapid growth of the local area.These works incorporated the installation of 2km of 400mm PE water main. This project was constructed under live traffic conditions with road crossing being undertaken at night so as not to disrupt traffic flow.

Project Details

80% of this watermain project was constructed using NDD boring techniques. This particular technique was chosen to minimise the impact on the local residents by reducing the disturbances to the existing landscaping and the need of heavy machinery.

 

The connection to the existing 375mm AC main was constructed at night in both locations to minimise disruptions to residents. There were additional challenges that needed to be accounted for due to the existing main being AC, we controlled for this using air monitors and supplementary hygiene measures.

Key challenges we overcame during this Sydney water infrastructure project include:

  • Live traffic conditions
  • Night works
  • Working around live services
  • Tight time restraints