Fluid Services was contracted by JK William to complete the construction the sewer and water infrastructure for a remote road side rest area at Mt Ousley Truck stop.
As there was no water & waste water available in the area we had to construct 2 6m deep holding well for with pump out facility’s and a 180m deep bore for the supply of water for the rest area. The power soured for the pump units was all supply for solar energy ad stored in batteries that was installed by us in the total scope.
Fluid Services handed over the water & waste water infrastructure over to RMS who now owns, operates and maintains the system.
The challenges faced constructing the wet wells were;